The Denmark Library project is currently progressing as planned but weather could become a factor over the next few months.
The concrete pours of curb and gutter in the parking lot have begun and the building footings have been poured. Electrical and plumbing piping are being installed in the building pad in preparation for the building concrete slab pours which are scheduled to happen the first two weeks of December. The steel for the building structure will arrive in early January.