Submitted by Sarah Reynolds
Lots can happen in a week when you are completing a library building, receiving furniture, erecting shelving, installing millwork, landscaping, coordinating technology, and preparing to receive a large shipment of books. Those variables allow us to hone our creativity, flexibility, and problem-solving skills!
With that in mind, several issues—such as back-ordered HVAC parts, delays in ceiling tile delivery, and Comcast connectivity problems—will delay our receipt of the certificate of occupancy (CO). As a result, we will need to postpone the branch’s grand opening. We plan to do a soft launch as soon as we’re ready, but we don’t have a set date yet. We’re aiming to have the grand opening sometime in January.
The building is still full of vendors and construction crews, so it wouldn’t be safe for the whole team to show up today when the first shipment of books arrives. Sarah booked the SF conference room for everyone to meet today for introductions, updates, and team building. Hopefully, fewer vendors will be around by Wednesday, and the whole team can start shelving books.
| Looking into the children's area from the entrance. The boxes on the left is where the Ask Us desk will be built. |
Until we get the CO, staff can only focus on tasks that physically prepare the building—like shelving books, setting up equipment, and hanging bulletin boards. Denmark team members won't be able to create displays, hold meetings, or sit at computers to work until the CO is issued.
| A different view of the children's area showing the back windows of the building and the shelves in progress. |
| Steve and Scot after prepping for the furniture delivery. |